AEP SOLAR TX 1, LLC

Solar

24/7 Renewable Baseload Power for Hyperscale AI Data Centers

Fully integrated 100–500 MW solar-thermal power platform — deployed in 12–14 months, not 3–5 years. Firm, dispatchable, carbon-free generation that runs 8,760 hours a year.

100–500

MW Per System

12–14

Months NTP to COD

8,760

Hrs/Yrs Baseload

25+

Year Asset Life

THE STSR PROCESS

Three Integrated Steps. One Reliable Outcome.

From sunlight to socket – our integrated architecture ensures efficient conversion, long-duration storage, and dependable power delivery around the clock.

image

Parabolic Trough Collection

Curved mirrors concentrate sunlight into high-temperature thermal heat.

image

Thermal Energy Storage (TESS)

Heat stored in a phase-change medium (<1% daily loss) enables round-the-clock dispatch, up to 8 -12 days.

image

Rankine Cycle Steam Turbines

Stored heat drives steam turbines — the same Rankine cycle producing 80% of world electricity today. N+1 modular units keep power flowing during STSR maintenance.

image

Firm, dispatchable, carbon-free generation — running 8,760 hours a year.

N+1 design isolates units for STSR maintenance without interrupting delivery to your data center.

8760

Hours of operation each year

N+ 1

Modular redundancy for uptime

100%

Carbon-free at point of use
AEP STSR PLATFORM VS. CONVENTIONAL SOLAR

Continuous renewable power, without the conventional limitations.

From generation and long-duration storage to dependable delivery, STSR provides firm renewable power around the clock.

Feature AEP STSR Platform Conventional Solar PV + Battery
Power Output
AEP STSR — Firm 24/7 baseload (8,760 hrs/yr) Conventional — Intermittent; battery limited
Storage Duration
AEP STSR — Overbuilt, long-duration thermal Conventional — 4–8 hour battery discharge
Daily Degradation
AEP STSR — Less than 1% Conventional — Significant battery fade
Asset Life
AEP STSR — 25+ years Conventional — 10–15 year battery replacement
Grid Dependency
AEP STSR — Fully off-grid capable Conventional — Requires grid backup at night
Land Footprint
AEP STSR — 100 MW in 12 acres (60× less) Conventional — Large land requirements
Fuel Source
AEP STSR — 100% renewable solar thermal Conventional — Solar PV + grid mix
Carbon
AEP STSR — Zero Scope 2 emissions (hourly) Conventional — Annual matching only
PROVEN EXECUTION

Grounded in operating performance data — not forecasts.

Multiple plants commissioned to date, headlined by a KBR-delivered 6 MW reference facility available for site visits and technical due diligence at any time.

6 MW reference plant — field construction in progress

6 MW reference plant

Field construction in progres
TESS & balance-of-plant equipment on site

Thermal Energy Storage (TESS)

TESS & balance-of-plant equipment on site
6 MW REFERENCE PLANT

Commissioned January 2026 — Operating Today

The KBR-delivered 6 MW reference plant is in commercial operation — a de-risked, fully commissioned commercial-scale asset available for site tours, walk-downs, and independent engineer review.

The 100MW project deploys the identical modular platform. Scaling from 100MW to 500MW is purely additive — drop in additional standardized modules. No re-engineering. No re-design. No first-of-a-kind risk.

Commercial-scale operation proven — not modeled

54-day field build demonstrated at reference plant

Modular platform engineered for 100–500MW replication

Zero first-of-a-kind risk on future deployments

Bankable performance record for IE and tax equity diligence

De-risked. Built, commissioned, operating today at scale.

DEPLOYMENT TIMELINE

FROM NTP TO COD

Typical Deployment Timeline: 12-14 Months

Step 1: Site Design & Engineering Site-adapted layout, foundation design, and interconnection engineering finalized on the pre-engineered KBR platform.
Step 2: Modular Manufacturing Turbine blocks, TESS, and Omni-DC handoff fabricated in parallel under KBR's Tier-1 EPC wrap and QA program.
Step 3: Field Installation Modules delivered and erected on schedule — foundations, collector field, TESS, and power block installed under fixed-price EPC.
Step 4: Commissioning & Handoff Full hot-fill, performance testing, and IE-witnessed acceptance prior to COD and 20-year PPA commencement.